It would take one machine 4 hours to complete a production order and another machine 2 hours to complete the same order. If both machines work simultaneously at their respective constant rates, the time taken to complete the same order is ________ hours. A. 2/3 B. 3/4 C. 4/3 D. 7/3

GATE 2019 · General Aptitude · Work Time · medium

Answer: 4/3 hours, which matches option C.

  1. Find individual rates: Rate_1 = 1/4 orders per hour (Machine 1, takes 4 hrs). Rate_2 = 1/2 orders per hour (Machine 2, takes 2 hrs).
  2. Add rates to get combined rate: R_combined = 1/4 + 1/2 = 1/4 + 2/4 = 3/4 orders per hour.
  3. Find combined time: T_combined = 1 / (3/4) = 4/3 hours.