IT was estimated that 42 men can complete a strip in a newly constructed highway connecting cities J and Q in 9 days. Due to an emergency, 14 men were sent to another project after 3 days of commencement of work. How many number of days, more than the original estimate, will be required to complete the strip?
A. 3 days
B. 5 days
C. 10 days
D. 13 days
GATE 2020 · General Aptitude · Work Time · medium
Answer: Extra days required = 3 days
Calculate total work in man-days: Total = 42 * 9 = 378 man-days.
Find work done in first 3 days: Work in first 3 days = 42 * 3 = 126 man-days.