5 skilled workers can build a wall in 20 days; 8 semi-skilled workers can build a wall in 25 days; 10 unskilled workers can build a wall in 30 days. If a team has 2 skilled, 6 semi-skilled and 5 unskilled workers, how long will the team take to build the wall? A. 20 days B. 18 days C. 16 days D. 15 days

GATE 2010 · General Aptitude · Work Time · medium

Answer: The team of 2 skilled, 6 semi-skilled and 5 unskilled workers will take 15 days to build the wall.

  1. Individual worker rates per day: Skilled: 1/(5*20) = 1/100. Semi-skilled: 1/(8*25) = 1/200. Unskilled: 1/(10*30) = 1/300
  2. Daily rate of the mixed team: = 2/100 + 6/200 + 5/300 = 6/300 + 9/300 + 5/300 = 20/300 = 1/15
  3. Days to build the wall: D = 1 / (1/15) = 15 days